Trump’s Tariffs and Trudeau’s Countermeasures: How to Protect Yourself in the Construction Industry
Posted on: June 28th, 2018 by

Introduction

The United States government, under the administration of Donald Trump, imposed tariffs on imports of Canadian steel and aluminum at the rate of 25% and 10% respectively, effective May 31, 2018. As a countermeasure, Canada’s Department of Finance intends to impose a reciprocal surtax (or analogous trade restrictive countermeasures) on imports of steel, aluminum, and other goods originating from the US in accordance with the Determination of Country of Origin for the Purposes of Marking Goods (NAFTA Countries) Regulations, (SOR/94-23). The countermeasures will affect only those goods imported from the US and are anticipated to take effect on July 1, 2018.

Table 1 and 2, available here: 18.06.28 Table of Tariffs, set out the entire list of imported goods that will be subject to the countermeasures. All Table 1 items will be subject to a 25% surtax and all Table 2 items will be subject to a 10% surtax. The various goods listed did not end up on the list by accident. These items were included because they are produced or manufactured in districts with an influential Republican or key Trump Cabinet Member.

For example, yogurt is the first item listed in Table 1. The Speaker of the United States House of Representatives, Paul Ryan, is a congressman from Wyoming, which is a large producer of yogurt. Additionally, the Senate majority leader Mitch McConnell is a US senator from Kentucky. Accordingly, it is by design that whiskies (which include Kentucky-based bourbons) will now be subject to a 10% surcharge. The intent was to apply pressure on districts with influential Republican incumbents.

The NAFTA negotiations are not scheduled to convene until after the Mexican presidential election is completed on July 1, 2018.  It is not difficult to envision a scenario where those negotiations drag on for a significant period of time. As a result, this escalating trade war between Canada and its largest trading partner could become the new reality for the Canadian construction industry, at least for the foreseeable future. This paper will focus on the implications for those importing steel and aluminum originating from the US for a Canadian project.

Standard Force Majeure Clauses Unlikely to Be of Assistance

The primary objective of entering into a construction contract is to allocate responsibilities (including contract price and scope of work) and also to allocate risk. The standard force majeure clause contained in a construction contract is a means of allocating risk. Essentially, a force majeure clause relieves a party from the obligation of fulfilling the responsibility under a construction contract should a certain event occur.

Force majeure clauses are often confused with the common law doctrine of frustration. Although there can be some overlap between the two concepts, they are distinct. The doctrine of frustration applies when the very essence, or fundamental aspect of the contract, becomes impossible to fulfill due to an unforeseen event outside of the control of either party. In contrast, a force majeure clause is a contractual provision intended to address situations that fall short of frustration. As a contractual provision, a force majeure clause can be flexible and tailored to address specific events. Additionally, unlike the doctrine of frustration which nullifies an agreement in its entirety, a force majeure clause can be designed to apply to a discreet, standalone obligation in the contract, as opposed to the contract as a whole. In essence, the provision addresses risks deemed unacceptable by the contracting parties.

Obviously, how the courts will interpret a force majeure clause depends entirely on the specific wording of that provision. However, many construction agreements contain boilerplate language. The key features of most force majeure clauses contain one or more of the following elements:

  • the specified event is beyond the control of the party;
  • the event prevents, in whole or in part, the performance of the contract;
  • the event makes performance of the contract substantially more difficult or more expensive to perform;
  • the triggering event was not caused by the party seeking to rely upon the clause; and
  • the claiming party has exercised reasonable diligence, or has attempted to mitigate the impact of the specified event.

The Supreme Court of Canada had an opportunity to review the law surrounding force majeure provisions over 40 years ago in Atlantic Paper Stock Ltd. v. St. Anne-Nackwawic Pulp and Paper Company Limited.[1] In that case, which remains the leading authority, Atlantic Paper contracted with St. Anne to supply 10,000 tonnes of waste paper (per year) for a 10 year period. That obligation was subject only to “an act of God, the Queens or public enemies, war, the authority of the law, labor unrest or strikes, the destruction of or damage to production facilities, or the non-availability of markets for pulp or corrugating medium.” St. Anne attempted to rely upon this underlined portion of the force majeure clause to get out of the agreement. The evidence established that there was an available market for pulp or corrugating medium, however, it just wasn’t profitable based on St. Anne’s operations. The Supreme Court determined that fell short of triggering the force majeure clause and ruled it was not proper to allow St. Anne to rely upon its soaring production costs to absolve it of contractual liability.

A more analogous situation to the current trade war occurred in Tom Jones & Sons Limited v. R, an Ontario High Court decision from 1982.[2] In that case, Tom Jones & Sons (“Tom Jones”) was the successful bidder for the construction of a building for the Government of Ontario. Shortly after the bid was accepted, the parties entered into a ground lease. Thereafter, Tom Jones advised the Government of Ontario that it could not arrange financing for the project.

The agreement between the parties contained a relatively standard force majeure clause that Tom Jones attempted to rely upon to rescind the contract. However, the court ruled that Tom Jones could not avoid its obligations to the Government of Ontario by relying upon the force majeure clause. It was determined from the evidence that it was not impossible for Tom Jones to obtain financing, but due to the volatility of interest rates in the money markets at the time, it could not get financing which would have led to the project being economically advantageous.

It is noteworthy that the courts have consistently determined that a project becoming unprofitable, or creating an economic hardship for one party, is not sufficient to trigger a force majeure clause. Again, while the analysis is fact specific depending on the specific wording of the force majeure clause, it is unlikely standard provisions will allow a party to be absolved of their responsibilities in an agreement due to the imposition of surtaxes and countermeasures, unless the force majeure clause is specifically written to apply to that situation.

Common Contractual Provisions That May Provide Relief: Price Acceleration Clauses for Duties and Taxes

Although not a strict force majeure clause, many standard construction agreements contain provisions dealing with government regulations, taxes and duties. For example, the CCDC 2 Stipulated Price Contract for 2008 contains the following provision:

Although “duties” is not defined in the agreement, it would appear that the surtax or countermeasures could be construed as a tax or a duty, which would give the contracting party an automatic right to increase the contract price to the same amount as the increased surtax or countermeasure. Obviously, this provision will give increased security and assistance to suppliers that entered into fixed-price arrangements before the imposition of the countermeasures.

There is nothing preventing a party from negotiating a similar provision into their contracts and to specifically reference the Government of Canada’s anticipated countermeasures in the clause.

Further, it should be noted agreements between owners and general contractors sometimes contain a provision entitling the owner to obtain the benefit of any tax exemption or tax rebate, and these provisions generally reference “customs” and “duties”.

As a result, depending on where you are in the construction pyramid, it is possible to flow through the surtax and countermeasures to the owner of the project. It is imperative that the contracts between the parties in the construction pyramid be reviewed to determine if this outcome is feasible.

Duty to Mitigate

Whether you are dealing with a force majeure clause, or a “duties and taxes price acceleration clause”, the parties still have a duty to mitigate any losses stemming from the non-performance of a contractual obligation. A well drafted force majeure clause will also contain an express duty to mitigate.

As a result, a party seeking to rely upon a price acceleration clause, or a force majeure clause, should ensure the material that is subject to the countermeasures cannot be sourced domestically or from a cheaper market.

Notice

Generally, a force majeure clause or price acceleration clause will contain an associated notice provision which creates a condition precedent to rely upon the clause. Strict adherence to any notice provision contained in the agreement is generally required by the courts. These notice provisions allow the responding party to mitigate the effects of the force majeure event.

In our particular example, the general contractor receiving goods subject to the countermeasures may have the option to de-scope the work from that subcontractor and source an alternative, cheaper supplier of the material. In certain situations, this might be preferable to being subject to the force majeure clause or price acceleration clause.

Conclusion

There is no guarantee that this trade dispute will be brief, and, there is no guarantee the dispute will not escalate. Further, standard boilerplate force majeure clauses are unlikely to provide relief for any party that is unexpectedly subject to the Government of Canada’s countermeasures. Price acceleration clauses addressing the countermeasures, or specifically tailored force majeure clauses, should be contemplated and inserted into construction agreements in order to purposely apportion the parties’ risk.

[1] Atlantic Paper Stock Ltd. v. St. Anne-Nackwawic Pulp and Paper Company Limited,[1975] 1 SCR 580.

[2] Tom Jones & Sons Limited v. R, 31 OR (2d) 649