On October 3 Advocates will welcome Felicia R. Lozon as an associate lawyer.

Felicia joins us after practicing in Ottawa with a large national firm. Felicia completed law school in 2020 after graduating with a mechanical engineering degree and working for a year in that field at 3M in London.

We are excited by the synergies that Felicia’s training and experience will bring to our clients’ needs.

We are also pleased to announce that Alicia Devos is now a Certified eDiscovery Specialist (CEDS). The CEDS process is administered by the Association of Certified eDiscovery Specialists (ACEDS) and requires 40 plus hours of training culminating in a four hour proctored examination. Alicia has been part of our team since December 2019 and has been responsible for managing various important firm projects. And we are excited to be able to announce our most important technology project yet.

In response to the ever-increasing volume of electronic records in litigation and third party vendor costs to manage that data, we have now implemented an in-house eDiscovery offering. We have licensed our own instance of iCONECT’s best-in-class “AI” enabled eDiscovery software and installed it at a Canadian data centre. By going straight to the vendor, Advocates is able to offer both reduced total cost and cost certainty to our clients without compromising the quality of the tool or the security and integrity of our client’s data. We are also able to provide client’s real time access to their data once it is in iCONECT via a user-friendly web interface, simplifying preparations for examinations for discovery and the process of answering undertakings.

The firm congratulates partners Kyle MacLean and Jim LeBer upon being recognized through the annual peer review survey process of Best Lawyers Canada. Kyle has been recognized by lawyers practicing Construction litigation, through Best Lawyers’ peer survey process, the results of which were released this month. We know how our client’s feel about Kyle’s skill and commitment to them. It is great to learn that other lawyers practicing in the construction sector are recognizing and endorsing him for those same talents.

Jim has again been recognized for his Construction litigation expertise, through the same process. He has received this honour every year since 2006. Based upon the results of this year’s peer survey he has also been selected as Best Lawyers’ “Lawyer of the Year” in the area of Construction Law for the geographical region of Southwestern Ontario.

Advocates continues to pursue the delivery of outstanding and creative solutions to complex problems, with our team’s specialty in the field of Construction Law.

The team at Advocates LLP is excited to be moving to a new purpose-built office space in London’s historic Selby Building, on “Richmond Row” a few blocks north of our current location.

The Selby Building was constructed in 1930 as a commercial / industrial building for the Selby Shoe company of Portsmouth Ohio. In 1939 London’s local Murray Shoe company merged with Selby Shoe to form Murray-Selby Shoes Ltd. which operated from the building for four decades. The Murray-Selby Shoe company closed in about 1979 and the building was converted in 1981 to commercial space. The interior of the building was opened up to a unique 4 story internal atrium which accents the large exterior windows in the original façade, making a distinct architectural statement for a repurposed historic building.

Advocates new offices are located on the fourth floor of the Selby Building. Commencing February 1, 2021 our new address will be 700 Richmond Street Suite 400 London ON N6A 5C7.

Advocates LLP is proud to announce that associate lawyer Eric Grigg has joined the firm as a partner.

Eric joined the firm just over four years ago, as an associate. Since that time he has proven himself to be an outstanding advocate, appearing on our client’s matters in motions court, at arbitration, in the Divisional Court and in the Court of Appeal. Eric’s analytical skills are highly valued by our team, helping us to deliver innovative and practical solutions for our clients facing complex commercial disputes. Eric’s practice runs the gamut from all manner of construction disputes to professional negligence actions, to various kinds of complex commercial contract and shareholder disputes. He likes the challenge of a gnarly problem.

We know that our clients are reassured by that enthusiasm. We welcome him into the partnership.

Executive Alert:  Advocates LLP argues that Notice of Delay given now and tied to Ontario’s March 17 declaration of a State of Emergency and related MOH social distancing directives – may allow you access to a compensable delay, rather than merely an excusable delay.

A PDF copy of this article may be downloaded here.

Overview

These are indeed challenging times. What lies ahead is unknown for all of us.  Things will be particularly challenging for the construction industry given the complexity of factors which must come together to ensure the successful completion of a project.  The construction industry makes significant contributions to our economy; and  so it is imperative that all participants in the industry work collaboratively to keep projects going, at least where it is safe to do so; and where projects are suspended, to manage any claims arising in an efficient and effective manner.   

In response to the many questions we have received from our clients over the last week or so, we have developed a “roadmap” to help guide you  through some potential legal impacts of COVID 19 and provide you with some recommendations to assist you as you navigate these uncertain times.

These comments are intended to help you in your consideration of the available steps to be taken in light of COVID 19 concerns. They are premised upon two common contract formats used by many of our clients in the ICI Sector. Our comments are of a general nature only and are not, and should not, be relied upon as legal advice.

Our whole team at Advocates remains “at work” though we are doing so remotely these days, to comply with both the declared state of Emergency and related Public Health orders. We are available to you to review your specific contract language and discuss your specific circumstances as together we seek to develop an optimal strategy to keep  your forces safe on site, and attempt to position your company for the challenging days ahead, to the extent that relief may be available under your own unique contract provisions.

Where Do You Start?

We are not experts in infectious diseases.  However, we do know that to avoid or curtail the spread of COVID 19 limiting or preventing close contact in confined spaces is essential.  And as we also know for some spaces, like restaurants and schools, the governments have mandated closures.  That has not been the case in the construction industry – yet.

How and/or whether you proceed with your particular project will be influenced by a number of factors; including the environment in which the construction is taking place.  For example: are you engaged in construction in an enclosed environment (ie: building construction); or, are you engaged in construction in a non-enclosed environment (ie. road building?). The risk profile will be different and unique to each project.

However, in consideration of how you move forward, we know you always recognize that the key factor in your analysis is the health and safety of your own workers, and the health and safety of all the persons on the jobsite, and the public at large. Your consideration of the health and safety of workers is both your moral obligation and also your legal right and obligation.

General Principles of Occupational Health and Safety

Occupational Health and Safety remains a foundational principle which will govern all conduct on the job site. As you well know you are obliged to take all reasonable steps to ensure your site is, and remains, safe for workers. Employees have the right to refuse to perform work where they hold a bona fide belief that they may not be safe.

Under the Occupational Health and Safety Act s.37, an Employer is obliged to disclose the presence of hazardous materials in the workplace.

If the project site is a functioning hospital facility and the Constructor cannot be satisfied that its work force is not at risk of exposure to individuals with COVID 19 this may form a basis for refusal to work. Such a contractor may have General Conditions such as those found under the CCDC2 contract which deal specifically with Hazardous Materials. Those provisions require careful consideration based on the specific facts of your job site, and we urge anyone contemplating relying upon these clauses to immediately obtain legal advice.

Specifically, under Part V of the Occupational Health and Safety Act – s. 43 (3): a worker may refuse to work, or to do particular work where they have reason to believe that the physical condition of the workplace is likely to endanger them. There are exceptions to this right that apply to workers whose work is inherently risky, or to those whose refusal would directly endanger the life, health or safety of others, such as police, firefighters, or hospital workers. In these challenging times, we are grateful for those who have chosen to assume these risks for the benefit of the greater good.

We have heard reports of workers in certain circumstances and on certain projects refusing to work over concerns about COVID 19 health and safety concerns at the job site. We are aware of concerns for emerging and pending labour shortages. Product supply shortages will inevitably follow, since the manufacturers and those downstream in the supply chain will face the same impacts on their own workforce, assuming they have managed to remain open and operational in this difficult time.

The Contract

Every contract is unique and the facts are often as important as the terms of the contract. Below we have highlighted common provisions contained in the CCDC -2 Contract and in OPSS Contracts that you should be aware of; and we have noted how such provisions may be applicable to the current issues at hand. Of course, standard contracts may have been amended by supplementary conditions, as such it is important to read your contract thoroughly before you take any steps. 

Giving Notice of Delay and Requesting Extensions of Time

The government of the Province of Ontario declared a State of Emergency on Tuesday March 17, 2020 closing many different businesses. It banned public events of more than 50 people in the declaration, which reinforced the Ministry of Health (“MOH”) directives to invoke social distancing measures, requiring people to remain a minimum of 2M from one another, and to self-isolate for 14 days in the event of illness or potential exposure to an ill person.

Maintaining a sustained work force, and also achieving historical productivity levels, seems to no longer be possible in the medium term. The full extent of the ongoing impacts cannot be determined, but there are and will continue to be real impacts to projects underway and those projects about to commence with the arrival of Spring conditions.

Regardless of your form of Contract, we encourage you to be familiar with the various notice provisions – including when you must provide notice for a claim and what details must be included in the claim. While these are unprecedented times, you do not want to risk being denied a claim for compensation or relief from penalty, for failure to provide notice in accordance with the contract.

CCDC 2 Contracts

These comments generally apply to clients constructing buildings where the likelihood of the work force having to operate in close quarters (<2M), or within a team in a more confined space seems generally to be greater than in the road and bridge building sectors.

The provincial government in the Province of Ontario declared its State of Emergency on Tuesday March 17, 2020 closing many different businesses and banning public events of more than 50 people and reinforcing the MOH’s declaration to invoke social distancing measures. This gives us a logical reference point to establish either the commencement of the delay under the CCDC2 GC 6.5.4 or alternatively to contemplate the threshold of “as soon as the need for an Extension of Time becomes evident” under GC 3.06.01 of the OPSS GC’s. It also anchors your notice to a series of events which we argue should be compensable.


Compensable Delay – GC 6.5.2

A number of General Conditions may be triggered by issues arising with COVID 19 concerns. Under CCDC-2 we consider that the least risky of the avenues open to the Contractor to give notice arises through GC 6.5 Delays. 

Under GC 6.5.2 you can argue that a stop work order has been issued not by a Court but by another “public authority”, in the form of the declaration that people must not gather in numbers larger than 50 and should not be in closer proximity than 2M from one another. If either of these limitations to the way in which work on your site can be carried out, has a practical consequence of impacting productivity or entirely precluding certain tasks, then notice of delay may be given. If the same provisions are expected to cause material shortages, notice can be given. If the 14 day self-isolation obligation (triggered under various scenarios) is expected to cause labour shortages, notice can be given.

Under this provision the Contractor may seek reimbursement from the Owner for the costs incurred as a result of the delay, in addition to being granted further time and therefore relief from liquidated damages or other delay based penalty claims by an Owner for late project completion.

You may expect from consultants or owners, an argument that the work has not been stopped by these “orders”, and that the GC 6.5.2 clause applies only to a total stoppage of work, not to “mere operational constraints” such as those imposed by Ontario’s declaration and MOH’s directives.

Our response to that is that these operational constraints do stop the work in both space and in time. They stop the work within specific job site locations – specifically for the second team member who would normally and most efficiently work within the 2M radius of every other worker then on site. They also stop the work of workers who feeling briefly ill but, unable to access any definitive test, must stay off work for two weeks, along with workers who, without being ill themselves are obliged to isolate due to potential of exposure to an untested individual who themselves felt ill or was subsequently diagnosed.

This is not a criticism of these measures, but a reflection that this new reality will produce labour shortages in a number of different ways which were not previously foreseeable. Tying your notice to the provincial declaration and MOH directives assists that argument.

GC 6.5.2 places this risk on the Owner. Since COVID 19 was not a risk contemplated by the parties, we believe it can reasonably be argued that it could not have been transferred to bidders at time of contract formation. We see this GC as the preferred approach to dealing with these consequences and any resulting delays. Timely notice then, may be critical.

Force Majeure – GC 6.5.3.4

The alternative ground for delay would be GC 6.5.3.4 for delays suffered due to any cause beyond the Contractor’s control, other than one resulting from a default or breach of the Contract by the Contractor. In that alternative scenario, the only relief is additional time with no compensation. It becomes an excusable but not compensable delay, which is not a contractor’s preferred course.

Critically – and in either case, Notice of the Delay must be given within 10 working days of commencement of the delay pursuant to GC 6.5.4.

The take-away here is that under CCDC-2 you must give Notice of Delay within 10 working days of commencement of the delay, and we recommend anchoring that Notice to Ontario’s March 17 Emergency Declaration and the related MOH directives on social distancing.

Concealed or Unknown Conditions – GC 6.4

There is a third avenue under CCDC 2 which invokes the provisions of the Hazardous substances General Conditions. We consider it to be a high risk strategy for a contractor to rely on this provision because the party responsible for the presence of the Hazardous substance on site is at risk of having to indemnify the other for the consequential cost impacts of managing that exposure. For that reason, we could only see it be given serious consideration by those contractors working at an active hospital site where patients with COVID 19 are passing close to the location of construction activities. Those circumstances arguably give rise to an identifiable and enhanced risk caused by the activities of the Owner at the site.

The argument to be followed in such a case would arise with a Notice under GC 6.4 of a Concealed or Unknown Condition at the place of work. It would be a GC 6.1.4.2 unanticipated “physical condition… of a nature which differ materially from those generally recognized as inherent in construction activities…”

To initiate this process the Contractor must give Notice within 5 days of the observance of the conditions. Hence an immediate decision to give that Notice must be made if this were to form the basis of the effort to seek time and compensation due to impacts. It should also be expected to lead to a process of engaging the Occupational Health and Safety Committee and Hospital Risk Management staff. It would be a protracted process, during which there would likely be at least a temporary suspension of work while the Owner attempted to put in place further strategies to properly deal with the hazardous conditions.

Under GC 6.4.4 it is contemplated that the unknown condition may relate to toxic substances, and if so, reference is then made to the operative provisions of GC 9.2 Toxic and Hazardous Substances

The challenge and risk arising once the Contractor directs the Owner into GC 9.2 is that the pendulum can swing both ways. The concept established by GC 9.2 is to compel the party which is found to have introduced the toxic substance to the site, to bear all the consequences of steps necessary to address the impacts from the substance. The language is broad. It could be argued to apply to both direct clean-up costs, and consequential delay costs. Caution is therefore urged, before initiating such a process. The circumstances where it might succeed are likely restricted to those where the facility is a known treatment center for COVID 19 patients supporting the inference that an elevated toxic risk, was being brought to bear on the project due to the Owner’s operations.

As you can see in the snip below, the GC 9.2 Toxic and Hazardous Substances sections also creates trailing obligations for indemnity, which should be a concern to any General Contractor.


OPSS GENERAL CONDITION CONTRACTS

We recognize different factors will generally be at play for our general contractors in the road and bridge building sector. Many projects are just about to begin work following winter shut down. They are mostly being constructed in open outside environments, and not enclosed quarters.

Regardless of these differences, our clients tell us they have the same reasonable fears about labour shortages, productivity impacts on labour when it is available, and pending material shortages or supply chain disruption. These realities are becoming apparent, and might be said by MTO or others, with hindsight, to have been evident from the date of the province’s Declaration of Emergency on March 17th.

We raise this concern now with you as our partner Jim LeBer argued a case in Court on February 5th 2020, over the proper interpretation and application of the MTO’s contract language over EOT’s and Liquidated Damages. The Judge’s decision in that case has not yet been released. However, one of the elements in dispute arose from the internal contradiction in the MTO EOT process in GC3.06.01  which requires on one hand that a request be made “as soon as the need for such extension becomes evident” while mandating the use of the prescribed form indicating the precise amount of time extension required.  Arguably, until the impact has been nearly fully sustained, you can’t know the precise duration of the impact and therefore declare “the length of extension required.” Which demand trumps: as soon as evident – or – when the length of extension required is known?

During argument in that Court process MTO’s lawyers declared that if “the length of extension required” cannot be determined then the Construction Industry should be submitting multiple EOT’s along the way, for a single delay cause, updating your anticipated length of extension required whenever it begins to appear likely your estimate will have been exceeded. MTO’s lawyers argued that is not contrary to the provision and is the practice that should be followed, rather than await greater certainty on the probable duration of the impact before submitting the EOT, assuming the need for an extension is becoming evident.

Whether the Judge accepts this position as a reasonable interpretation of what the contractor should do, our message to the Industry is clear:

MTO has argued you have failed to give timely notice and your EOT should be rejected when notwithstanding uncertainty about duration, a Contractor did not submit the EOT as soon as it can be said that the need became evident. We strongly recommend submitting an EOT now based on the March 17 Declaration of Emergency and related MOH directives on social distancing, and the resulting and known impacts of those constraints.

MTO says you must do so even without a reliable prediction of the length of extension required. This is not a practice we at Advocates have typically seen adopted by our clients, and so we bring it to your attention. The response of MTO to such notices, remains to be seen. We will be keen to observe how they will be managed by CA’s and MTO staff as well.

The language of GC 3.07.01 (d) has similarities to those discussed above in the context of CCDC2 language about public authorities – AND – is also a compensable delay.

 “A stop work order issued by a court or public authority, provided that such order was not issued as the result of an act or omission of the Contractor…” 

We believe that the same consequences of Ontario’s March 17, 2020 State of Emergency declaration and related MOH directives can be said to flow from those orders issued which stop work both within the available space at the project site, and across time for workers trying to responsibly comply with the self-isolation directive. We repeat those comments again below.

Advocates argue that a stop work order has been issued by another “public authority”, in the form of the mandate that people must not gather in numbers larger than 50 and should not be in closer proximity than 2M from one another. If either of these limitations to the way in which work on your site can be carried out, has a practical consequence of impacting productivity or entirely precluding certain tasks, then notice of delay can be given. If the same provisions are expected to cause material shortages, notice can be given. If the 14 day self-isolation obligation is expected to cause labour shortages, notice can be given.

We recommend submitting a Request for Extension of Time caused by the constraints imposed by the Declaration of Emergency of March 17th and related MOH directives, with a best “guestimate” of the length of extension and an affirmative statement that the estimate of the length of time required will be revised and updated as further certainty is gained in the passage of time.

The consequence of submitting an EOT request is that the obligation to keep DWR’s is triggered immediately for all work potentially impacted by the delay.

We frequently see claims rejected by MTO for a failure to prepare, submit and reconcile  DWR’s weekly on any project where a delay is believed to be ongoing, and where notice of an EOT has been given, (or is subsequently given at some later date).

Our recommendation is to submit your EOT now and begin immediately keeping DWR’s for all tasks which have the potential of being impacted by the impending delay. Given the wide ranging nature of the delays which could arise to both labour and material across multiple subcontractor groups, it looks like all tasks could be tracked in the DWR’s you are going to be submitting.

Conclusion

The team at Advocates remain available while working from our various remote locations. We are just a video call away. We’d be glad to hear from you! Let us know if these comments have raised specific questions or concerns for you. We are ready to review your own contract’s specific language, to consider its supplementary general conditions, and the unique facts you are facing on your job site, if you need legal advice about alternatives you may want to implement now, to preserve your options going forward.

A PDF copy of this article may be downloaded here.

The firm is excited to announce that Enje Daniels has joined our team as an associate. Enje comes to the firm having received her law degree from Western’s Law School in June 2018. She also has a Bachelor of Commerce degree from the DeGroote School of Business at McMaster. Having proven herself in the academic world, she is looking forward to “getting down to business”.

Like many of our clients Enje has an entrepreneurial bent, owning and operating her own photography business, while in law school. She has also travelled widely and is a self-described “foodie”. You can ask her about that!

We know that our clients will enjoy getting to know Enje as they work together with her to advance their causes and defend their interests.

Welcome to the team Enje!

Advocates LLP is proud to announce that associate lawyers Jeff Van Bakel and Kyle MacLean have joined the firm as partners.

Kyle began working with us at the end of his articling year. Since then he has consistently demonstrated his growing skills, aptitude for innovation and sound judgment while working with our team on all aspects of complex commercial disputes. Our clients have recognized his talents, and the group of those for whom he has taken on leading roles continues to expand. We are excited to affirm our great expectations of Kyle, as we welcome him into the partnership. Kyle practices in the areas of Construction Litigation and Professional Negligence.

Jeff came to us 15 months ago from Toronto where he spent 10 years working in a large and diverse commercial litigation firm. Jeff’s practice involved commercial, construction and professional disputes. He had already developed solid well-honed skills that he was looking to apply within Advocates’ practice areas serving our core group of commercial clients. Jeff’s move back to his family roots in the London area has proven to be beneficial for Advocates’ clients, while also strengthening the depth of our team. Jeff practices in the areas of Professional Negligence, Construction Litigation and Shareholder Disputes.

Welcome to the partnership Kyle and Jeff!

Advocates LLP is pleased to congratulate our partner Marcia Oliver on her recent election to Secretary of the Canadian Bar Association’s National Construction & Infrastructure Law Section Executive. The Section focuses its efforts on finding solutions to legal issues impacting the Canadian construction industry. A Certified Specialist in Construction Law and a Fellow of the Canadian College of Construction Lawyers, Marcia brings a wealth of construction law experience to this position.

The firm is proud to announce that Marcia Oliver has been awarded the Joel Kuchar Award for Professionalism and Civility. This annual award is given to two lawyers chosen by members of the legal profession, who have “consistently demonstrated exemplary commitment to the ideals of professionalism and civility in the practice of law.” We at the firm always recognized those qualities in our partner, but it is gratifying when that recognition of Marcia’s outstanding character comes from our peers at the Ontario Bar Association. The formal presentation of the awards to Marcia and the other recipient lawyer Lee Akazaki will take place next week at the OBA’s Annual Awards Gala in Toronto.

Congratulations Marcia – We’re proud of you!

The firm’s team of Eric Grigg, Kyle MacLean, Jeff Van Bakel, and Jim LeBer will be teaching a day-long workshop at the Ontario Road Builders Association annual “Road Building Academy” in Toronto on Tuesday February 27th. The workshop is principally focused upon contractor’s strategies for dealing with the Ministry of Transportation, under the revised Dispute Resolution procedures incorporating the new Referee process.

It is a process the firm has frequently coached contractors through, since it was first introduced in February 2016, and now forms part of the OPPS November 2016 General Conditions of Contract.